Quantities of earthworks are automatically calculated and a report provided showing progressive and total volumes along the sections.
You can specify a depth of 'topsoil stripping' if needed, and an report seen below is generated.
Road
Works Volumes. JOB:
roadtut4
Stripping Depth 0.150 metres
Stripping Area
9302.923 sq metres
Stripping Volume
1395.438 metres cubed
________________________________________________________________________
CUT
FILL
TOTAL
Chainage
Area Vol
Prog Area
Vol Prog
Volume
________________________________________________________________________
0.000 0.0
0 0
0.0 0
0
0
20.000
-21.2 -212
-212 0.0
0 0
-211
40.000
-26.2 -473
-685 0.0
0 1
-684
60.000
-29.2 -554
-1239 11.6
116 117
-1122
80.000
-29.0 -583
-1821 29.0
406 523
-1298
100.000
-16.7 -457
-2278 34.5
636 1159
-1119
120.000
-4.7 -213
-2492 48.1
826 1985
-506
140.000
-4.4 -91
-2582 43.0
911 2896
314
160.000
-16.1 -205
-2787 10.9
539 3435
648
180.000
-77.4 -935
-3722 0.0
109 3544
-178
200.000
-174.7 -2522 -6244
0.0 0
3544 -2700
220.000
-139.2 -3139 -9383
0.0 0
3545 -5838
240.000
0.0 -1392
-10775 149.2
1493 5037
-5738
260.000
0.0 0
-10775 368.7
5180 10217
-558
280.000
0.0 0
-10775 121.1
4898 15115
4341
283.968
0.0 0
-10775 64.2
368 15483
4708
290.000
-9.7 -29
-10804 0.0
194 15677
4873
300.000
-157.6 -836 -11640 0.0
0 15677
4037
310.000
-190.6 -1741 -13381 0.0
0 15677
2296
320.000
-148.1 -1693 -15074 0.0
0 15677
603
330.000
-121.4 -1347 -16422 0.0
0 15678
-744
340.000
-85.7 -1036
-17457 0.0
0 15678
-1780